After the footings were poured we added about 6" of gravel
Then a layer of plastic to keep moisture from coming up into the slab
Then a layer of insulation
Then sand and rebar
Contralo and Samuel did most of the inner slab work at Mike Wright's direction
Then I added the radiant floor tubing
Rick Wilson came by and helped pressure test the tubing and on Friday afternoon we received approval from the building department to proceed with the slab pour, scheduled for Monday.