The foundation coming together.

After the footings were poured we added about 6" of gravel


Then a layer of plastic to keep moisture from coming up into the slab


Then a layer of insulation


Then sand and rebar


Contralo and Samuel did most of the inner slab work at Mike Wright's direction


Then I added the radiant floor tubing


Rick Wilson came by and helped pressure test the tubing and on Friday afternoon we received approval from the building department to proceed with the slab pour, scheduled for Monday.