Monday, May 19, 2008
Concrete Stain woes
Steve Ramirez and Louis prepping the floor.
First application of stain
Applying stain
Buffing the stain into the concrete (we should have known there was going to be a problem as we went through ten or more of these polishing pads)
Five days later the darker color of the stain was still not dry. Here Steve applies caulking into the score pattern - this too was not a good idea, we ended up digging out the caulking and applying grout.
Monday, May 5, 2008
More trenches
Here one truck is dumping sand while in the background a cement mixer is pouring concrete to repair the sidewalk.
After much digging I was able to find the sewer pipe coming from the house to which we would connect.
Trench for sewer and water.
Trench for gas and electric
Gas and electric in. We were able to lay all four services - gas, electric, water, and sewer - in one day.
After setting the pipe, sand is thrown in and packed down
All of which had to be done by hand as there was too much dirt for the tractor or excavator to work around.
Getting back to 'normal' with trenches filled in.
A backyard is finally starting to take shape.
Monday, April 28, 2008
The Big Dig
The problem (read $$$) was that we had only a 2" underground conduit coming into the house and needed a 3" conduit for 200 amp service. This meant digging up the street and putting in a new conduit.
After waiting 3 months for PG&E to produce a 'trench package' I went to four companies for bids. The highest was $16,000 and lowest $7,000. Fortunately the low bid came from a very reputable company and a week later the work was on. (On top of this were PG&E's administration, engineering and cabling fees of $4,500)
First, the dig area was marked so that service companies like the water department, telephone, cable, and gas, could come out and identify where their pipes and cables run.
There was a power pole closer to the house however according to PG&E there were not enough connections available on it, so instead of a 50' dig we had to go 112'.
I installed the new panel on the side of the garage.
Cutting the concrete.
Jackhammering the sidewalk
The last section had to be dug by hand
Asphalt removed
I should mention that this job created a bit of chaos in the neighborhood. We're lucky we live on a cul-de-sac so there's not a lot of through traffic but while some parts of the project went quickly, all of the above photos were done in a day, the entire project from start to finish was over two weeks. J. Johnson & Company, the contractor, were experienced and capable and covered up the trench with steel plates, even putting asphalt around the steel plates to make the bump less dramatic.
4' trench dug by backhoe.
Covered up and paved.
Friday, April 18, 2008
The Amazing Kevin Schromm
I called Kevin in late February and he told me that he would not be available until April, that he was taking March off to be with his wife and soon to be born child. The timing worked out fine as sheetrock was just wrapping up (One sour note on the sheetrock guys - while I had informed every other work crew that if they needed to use the bathroom they could use the one in the main house as long as I was there and that there is a park nearby with public restrooms if I was away. The sheetrock finish crew showed up unannounced while I was at the hardware store and, in need, peed into the shower drain - which was plugged up as the drainpipes were not yet connected. Kevin showed up soon after to set up for tile work and found a puddle of urine on the shower floor. By the time I got back the sheetrock guys were on their way out after being confronted by Kevin, swearing that they had no idea were the pee came from and having hastily finished up. I cleaned out the pee and gave Joe Faria a call who said that he would deal with the guys.)
Most tile guys use hardirock or cement board for backing. Kevin prefers the old-school method of floating the entire backing with mortar. He has an array of wood slats in various lengths to screed the walls perfectly smooth and square.
Together with Kevin we had picked out a composite of recycled glass and slate, 1" x 1" tiles in 12" x 12" sheets. However the sheets come with the front side of the tile glued to paper so you can't see what the exact pattern will be and the problem 'we' ran into was that some sheets would have mostly light colored slate while others had mostly dark colored slate. Being the perfectionist, Kevin picked out tiles by hand and re-arranged to make the color pattern even across the entire shower stall.
Re-fixing individual tiles
It was a big job and while we both thought that the finished product looked great when asked Kevin said that because of the inconsistencies in the color patterns he wouldn't work with tiles from that manufacturer again.
The final look.
Wednesday, March 19, 2008
Insulation and Sheetrock
Insulation is R-19 on the walls and R-30 in the ceiling. I, of course, wanted to do the green thing, which in the case of insulation would have been to use a soy based spray foam insulation, or cellulose (newspaper). However there were few contractors that did wet-spray cellulose. More common is dry sprayed cellulose in attics. And the bids for spray foam were five times the cost of fiberglass. I took some consolation that the fiberglass insulation was formaldehyde-free.
I solicited a couple of bids for sheetrock but my friend Rick Wilson, with whom I consult frequently, told me that I wouldn't get a lower bid than from Joe Faria, and he was right. The first bid was $6,300 and Faria's bid was $3,600!
After cleaning up the mess.
I was surprised by how small the rooms suddenly became once the sheet rock was up.
Tuesday, March 11, 2008
Oh so close to calling for a rough electric and plumbing inspection
Like this.
In progress, but this will run directly to the tankless water heater.
Mike Wright graciously offered to put in the shower dam and blocking. While there he said that he could also apply the mortar that sits below the shower liner. However, we buried the plumbing flange. The tile guy is coming out tomorrow to remedy. Moral - let each sub do what they do best.
Thursday, February 28, 2008
Panels on, rough electric and plumbing almost done
Doesn't look much different from January, does it?
Fan and heat lamp in bathroom
Low volt (telephone, cable, data) and high volt electric panels
Monday, February 25, 2008
Winter Diversion
Wednesday, February 13, 2008
Reset Solar Stand-offs
18 deg tilt:
Month by Month Summary of Sun on Collector
(100% sunny weather)
Collector Area: 1.0 (sqft)
Collector Azimuth: 0.0 (deg) measured from South
Collector Tilt: 18.0 (deg) measured from horiz
Latitude: 39.0 (deg)
Altitude above SL: 0.0 (ft) Above Sea Level
Date ---- Sun ------------
Month Day Direct Di- Total Direct Difuse Total
Normal fuse
1 21 2234 130 2364 1349 127 1475 <---
2 21 2635 158 2793 1710 154 1864
3 21 2931 208 3139 2013 203 2216
4 21 3095 302 3396 2147 294 2441
5 21 3155 383 3538 2188 374 2561
6 21 3164 423 3587 2174 413 2587
7 21 3055 415 3470 2125 405 2530
8 21 2914 354 3268 2040 345 2386
9 21 2727 253 2981 1891 247 2138
10 21 2464 179 2642 1610 174 1784
11 21 2164 136 2300 1306 133 1438
12 21 2032 117 2149 1175 114 1289
Sum 32570 3057 35627 21726 2983 24708
Radiation in BTU/day
54 deg tilt:
Month by Month Summary of Sun on Collector (100% sunny weather)
Collector Area: 1.0 (sqft)
Collector Azimuth: 0.0 (deg) measured from South Collector Tilt: 54.0 (deg)
measured from horiz Latitude: 39.0 (deg)
Altitude above SL: 0.0 (ft) Above Sea Level
Date ---- Sun ------------
Month Day Direct Di- Total Direct Difuse Total
Normal fuse
1 21 2234 130 2364 1871 103 1974
2 21 2635 158 2793 2078 125 2203
3 21 2931 208 3139 2082 165 2248
4 21 3095 302 3396 1833 239 2072
5 21 3155 383 3538 1604 304 1907
6 21 3164 423 3587 1496 336 1832
7 21 3055 415 3470 1548 330 1877
8 21 2914 354 3268 1734 281 2015
9 21 2727 253 2981 1944 201 2146
10 21 2464 179 2642 1964 142 2106
11 21 2164 136 2300 1816 108 1924
12 21 2032 117 2149 1724 93 1817
Sum 32570 3057 35627 21692 2427 24119
Radiation in BTU/day
/Gary
-------------------------
Problem was that if I raised the panels in the originally planned location, in the middle of two rows of solar PV panels, I would end up shading the PV panels in the morning and late afternoon. So I re-arranged the standoffs with the solar hot water panels to be mounted horizontally above the PV panels.
I had great help from Don Hiatt, of Hiatt roofing and his assistant Rick (?)
Also shown here are the tilt legs for the panels
A lovely fire sprinkler control valve is placed on the side of the house
Wiring panel
Electrical Wiring
Wednesday, January 16, 2008
Big Update - New Camera
Roof shingled, windows and doors in, papered and lathed
Drain vent plumbing
Patio Doors
Washer/Dryer hook up
Electrical boxes rough placement
Bath vanity plumbing
Rough placement of in-ceiling light fixtures
Solar stand-offs placed prior to roofing
What's embarrassing is how little has been done between when these pictures were taken and now, March 11.